Assigned
Status Update
Comments
sa...@google.com <sa...@google.com>
sa...@google.com <sa...@google.com> #2
I have forwarded this request to the engineering team. We will update this issue with any progress updates and a resolution.
Description
SLOs for monitoring support two types for setting the period: rolling_window (Duration) or calendar_period (calendarPeriod). The max for either of these, based on the SLO docs, is 30 days or a MONTH, respectively. We'd like to raise this so SLOs are trackable for 90 days
What you expected to happen:
SLOs can be tracked for 90 days instead of just 30
Steps to reproduce:
Configure an SLO and try to set the period to 90 days
Other information (workarounds you have tried, documentation consulted, etc):
A workaround exists to set up a pub/sub to BQ which exports the metric on a schedule and the reporting can be built from that table but for external reporting to clients, having the metric tool be a built in from GCP instead of homegrown solution provides greater assurance.